A quick guide about the SAP C_ACTIVATE13 Certification Exam Cost, duration and passing score

Information about the time duration, no. of questions, passing score, and language is discussed in detail, in the C_ACTIVATE13 Dumps. Overview of all that info is given as follows:

  • The passing score: 65%
  • Time Duration: 180 minutes
  • Number of Questions: 80 questions
  • Languages: English, Russian, Japanese, and Chinese

 

NEW QUESTION 40
What do you do during an iterative approach to build a solution?
Please choose the correct answer.
Response:

  • A. Provide a working solution only at the end of the release
  • B. Build the solution module by module
  • C. Deliver a prototype of the solution
  • D. Include frequent inspection check-points

Answer: D

 

NEW QUESTION 41
Which of the following are available in the initial SAP Methodologies JAM Page?
There are 2 correct answers to this question.
Response:

  • A. Roadmaps
  • B. Task description
  • C. Summary
  • D. Accelerators

Answer: A,D

 

NEW QUESTION 42
What can you do in the SAP Roadmap Viewer tool?
Please choose the correct answer.
Response:

  • A. Comment on Deliverables and Tasks within Roadmaps.
  • B. Create a customer-specific version of a roadmap.
  • C. Navigate detailed Solution Implementation Roadmaps.
  • D. Download full roadmap content for offline navigation.

Answer: C

 

NEW QUESTION 43
Which artifacts are created within application design and configuration workstream in the explore Phase of the
"New implementation of SAP S/4HANA"
There are 3 correct answers to this question

  • A. Project procedure-mock-up modeling
  • B. Organisation structure specification
  • C. Delta requirements list-register
  • D. Detailed design-business process
  • E. Roles and authorizations management concept

Answer: C,D,E

 

NEW QUESTION 44
Which deliverable is specific to on-premise and NOT for the cloud?
Please choose the correct answer.
Response:

  • A. Adaptation Specification
  • B. Knowledge Transfer
  • C. Learning Needs Analysis
  • D. Technical Design Solution

Answer: B

 

NEW QUESTION 45
Why is there NO sandbox system in the "New Implementation of SAP S/4HANA cloud Single Tenant?

  • A. Because the fit-to-standard workshop is conducted using the Q system
  • B. Because the project team uses the DEV system to confirm solution fit
  • C. Because SAP S/4HANA cloud, single tenant edition, contains predefined business
  • D. Because the customer may use the SAP model company

Answer: C

 

NEW QUESTION 46
What is the purpose of a firm-up sprint?
Please choose the correct answer.
Response:

  • A. To revise a release plan and sprint plan
  • B. To run end-to-end integration test
  • C. To perform String test
  • D. To demonstrate functionality from previous sprint

Answer: C

 

NEW QUESTION 47
What is the best target deployment option of SAP S/4HANA for the "System Conversion" transition path?
Please choose the correct answer.
Response:

  • A. SAP S/4HANA Cloud
  • B. Hybrid of SAP S/4HANA Cloud and SAP S/4HANA
  • C. SAP S/4HANA
  • D. SAP C/4HANA

Answer: B

 

NEW QUESTION 48
Which new project roles are introduced with the SAP Activate methodology for the Agile delivery approach?
There are 2 correct answers to this question.

  • A. Scrum master
  • B. Product owner
  • C. Design thinking coach
  • D. Integration lead

Answer: A,B

 

NEW QUESTION 49
How would you describe the Realize phase in the "New Implementation of SAP S/4HANA" transition path?
Please choose the correct answer.
Response:

  • A. Configure and develop
  • B. Configure and adjust custom code
  • C. Configure
  • D. Configuration copy

Answer: C

 

NEW QUESTION 50
Which of the following Key Deliverables do you complete in the Solution Design work stream in the Explore phase?
There are 3 correct answers to this question.
Response:

  • A. Solution Scope and Value Determination
  • B. Design for the Gaps and Deltas
  • C. Data Migration Approach
  • D. Validation Workshops
  • E. Baseline Build

Answer: B,C,D

 

NEW QUESTION 51
How often will an upgrade be performed on an SAP S/4HANA cloud single tenant edition environment?

  • A. One upgrade and two feature packs per year
  • B. Every quarter
  • C. Every year
  • D. Schedule is defined by service level agreement for SAP HANA enterprise cloud and SAP S/4HANA Cloud single tenant edition services.

Answer: D

 

NEW QUESTION 52
What is the difference between the "System Conversion and the "New Implementation of SAP S/4HANA" transition paths?
There are 2 correct answers to this question.
Response:

  • A. In the Realize phase, data is converted and NOT migrated for System Conversion.
  • B. SSCUls are used in System Conversion for configuring SAP S/4HANA through the Manage Your Solution app.
  • C. In the Realize phase, custom code is adjusted rather than developed for System Conversion.
  • D. There are different upgrade cycles.

Answer: A,C

 

NEW QUESTION 53
What tool provides sizing estimations for the "System Conversion" transition path?
Please choose the correct answer.
Response:

  • A. SAP Transformation Navigator
  • B. SAP Best Practices Explorer
  • C. Scope and Effort Analyzer
  • D. SAP Readiness Check

Answer: D

 

NEW QUESTION 54
Which estimation technique can be used in agile delivery approach to size the user Stories during sprint planning?

  • A. Detailed bottom-up effort estimate by the scrum master in story points based on the User story complexity
  • B. Product owners relative estimate of the effort that will be needed to implement the user story
  • C. Detailed bottom-up effort estimate that breaks each user story up into hours or shorter tasks
  • D. Relative estimate in ideal person days that reflects the best estimate provided By the project team

Answer: D

 

NEW QUESTION 55
What is the purpose of the solution validation activity in the explore phase? There are 3 correct answers to this question Response:

  • A. Log additional scope items
  • B. Educate project participate
  • C. Challenge changes to standard
  • D. Verify technical installation
  • E. Identify gaps

Answer: A,C,E

 

NEW QUESTION 56
Which of the following are part of the 10 SAP quality principle?
There are 2 correct answers to this question

  • A. Use standard functionality optionally
  • B. Start scoping early
  • C. Plan phase at a time
  • D. Achieve production readiness

Answer: B,D

 

NEW QUESTION 57
What are two important approaches, based on the control centre concept, that SAP Proposes to use for streamlined implementation and operations?
There are 2 correct answers to this question

  • A. Run SAP like a factory
  • B. Build SAP like a factory
  • C. Always connected
  • D. Intelligent enterprise

Answer: A,B

 

NEW QUESTION 58
Which of the following will help you avoid modification of standard functionality in SAP S/4HANA Cloud, Single Tenant Edit on?
There are 3 correct answers to this question.
Response:

  • A. The 5 Golden Rules
  • B. The Side-by-Side Extensibility Option (such as SAP Cloud Platform)
  • C. SAP Code Inspector
  • D. Contract restrictions in SAP HANA Enterprise Cloud and SAP S/4HANA Cloud, Single Tenant Edition
  • E. A developer key

Answer: A,B,D

 

NEW QUESTION 59
Which end-to-end turn-key Application Lifecycle Management (ALM) solution can support you in managing requirements and software development for large, Agile projects?
Please choose the correct answer.
Response:

  • A. Solution Manager Test Suite
  • B. Change Request Management
  • C. Requirement Management
  • D. Focused Build

Answer: D

 

NEW QUESTION 60
In which SAP Activate methodology phase does the team identify and design functional quick wins in scope of the conversion project?
Please choose the correct answer.
Response:

  • A. Realize
  • B. Prepare
  • C. Deploy
  • D. Explore

Answer: D

 

NEW QUESTION 61
Who determines the tasks that are required to complete the committed backlog items in a sprint?

  • A. Scrum master
  • B. Product owner
  • C. Project team
  • D. Project manager

Answer: B

 

NEW QUESTION 62
According to the Definition of Done, which activity must be completed for each sprint?
Please choose the correct answer.
Response:

  • A. End user training must be delivered
  • B. The Solution must be built and configured in the development system (DEV)
  • C. Functionality must be released to the business
  • D. Functionality must be tested in the Quality system (QAS)

Answer: B

 