To take the PRINCE2 Agile Foundation Certification Exam, candidates must have a basic understanding of project management principles and some experience working on projects. PRINCE2-Agile-Foundation exam consists of 50 multiple-choice questions that must be completed within one hour. Candidates who successfully pass the exam will receive the PRINCE2 Agile Foundation certification, which is valid for three years.

 

NEW QUESTION # 50
Which process can take place during a release review workshop?

  • A. Controlling a stage
  • B. Directing a project
  • C. Managing a stage boundary
  • D. Managing product delivery

Answer: D


NEW QUESTION # 51
According to PRINCE2 Agile, which form of communication shows that a team is vibrant and interactive?

  • A. Using meeting minutes to share decisions
  • B. Using social media to reach more people
  • C. Using visualization to display information
  • D. Using email to document discussions

Answer: C


NEW QUESTION # 52
When should PRINCE2 Agile be used?

  • A. When an established team performs product maintenance
  • B. When delivering an ongoing service to a customer
  • C. When simple requests to update a product are implemented
  • D. When a team is created to deliver a specific product

Answer: A


NEW QUESTION # 53
What is typically displayed on a board to show progress to people working on a project?

  • A. User story
  • B. Agilometer assessment
  • C. Product backlog
  • D. Information radiator

Answer: D


NEW QUESTION # 54
When tailoring PRINCE2, what does PRINCE2 Agile guidance cover?

  • A. How to decide whether PRINCE2 is appropriate
  • B. How to select which Agile framework should be favoured
  • C. How to calculate the project budget and cost tolerance
  • D. How to adapt the PRINCE2 management products

Answer: D


NEW QUESTION # 55
What is the definition of a timebox?

  • A. A tool to write a requirement in the form of who, what and why
  • B. A description of the rate of progress a team is making
  • C. A regular event that looks at how processes can be improved
  • D. A period where work is carried out to achieve a goal

Answer: D


NEW QUESTION # 56
Which is a purpose of the plans theme?

  • A. To identify any deviations from the project's objectives
  • B. To communicate the approach for delivering products
  • C. To control any approved changes to the baseline
  • D. To monitor actual achievements against those planned

Answer: B


NEW QUESTION # 57
How is the 'learn from experience' principle applied in an agile context?

  • A. By using the Agilometer to assess risks associated with the agile way of working
  • B. By ensuring control through lots of short stages during innovative projects
  • C. By prioritizing quality criteria to focus the project on the delivery of value
  • D. By continual customer involvement to obtain feedback during the project

Answer: D


NEW QUESTION # 58
In Lean Startup, what is based on the concept of 'learn the most with the least effort'?

  • A. A minimum viable product
  • B. A set of criteria to determine whether work can be started
  • C. A structured, timeboxed event
  • D. A measurement of lead times

Answer: A


NEW QUESTION # 59
To help with prioritization, what is MOST important when understanding the difference between scope and quality?

  • A. Creating non-functional requirements with user stories
  • B. Defining non-functional requirements before functional requirements
  • C. Combining functional and non-functional requirements
  • D. Differentiating functional from non-functional requirements

Answer: D


NEW QUESTION # 60
Why are team working agreement produced?

  • A. To create structure so that the team manager can assess individual performance
  • B. To ensure that the delivery team members comply with company policy
  • C. To make the team rules visible to the project manager for monitoring purposes
  • D. To evolve the effectiveness and behaviors of the self-organizing team by agreeing values

Answer: D

Explanation:
Reference https://publications.axelos.com/prince2agile2016/content.aspx?page=pra_126&showNav=true&expandNav=true


NEW QUESTION # 61
Which is a purpose of the 'controlling stage' process?

  • A. To draft the plan for the next stage's work
  • B. To execute and deliver the project product
  • C. To establish whether the project is complete
  • D. To report stage progress to the project board

Answer: D

Explanation:
Reference:
%20remains%20within%20tolerance.&text=Risks%20and%20issues%20are%20kept%20under%20control


NEW QUESTION # 62
Which statement explains the setting of the cost tolerance for a project in an agile context?

  • A. Cost tolerance is flexed
  • B. Cost tolerance can be fixed and flexed
  • C. Cost tolerance is fixed
  • D. Cost tolerance can be fixed or flexed

Answer: A


NEW QUESTION # 63
Which statement describes how the PRINCE2 'starting up a project' process can be applied in an agile environment?

  • A. PRINCE2 is predictive, but not emergent
  • B. PRINCE2 requires a disruptive start to a project
  • C. PRINCE2 is predictive and can be emergent
  • D. PRINCE2 requires a lengthy start to a project

Answer: C


NEW QUESTION # 64
In which area is Agile strongest when blending with PRINCE2?

  • A. Product delivery
  • B. Project management
  • C. Product management
  • D. Project direction

Answer: A


NEW QUESTION # 65
Which TWO statements describe a purpose of the business case?
1) To define the acceptance criteria for what the project must deliver.
2) To transfer responsibility for the work to the appropriate delivery team.
3) To document how significant risks will affect the expected project benefits.
4) To outline how and when the anticipated benefits can be measured.

  • A. 1 and 2
  • B. 3 and 4
  • C. 2 and 3
  • D. 1 and 4

Answer: B


NEW QUESTION # 66
......


PRINCE2 PRINCE2-Agile-Foundation (PRINCE2 Agile Foundation) Certification Exam is designed to test the knowledge and understanding of individuals in the concepts of PRINCE2 and Agile methodologies. PRINCE2 Agile Foundation certification is ideal for individuals who wish to develop their understanding of project management methodologies and enhance their expertise in managing projects using a combination of PRINCE2 and Agile methodologies.

 

Verified PRINCE2-Agile-Foundation exam dumps Q&As with Correct 94 Questions and Answers: https://examtests.passcollection.com/PRINCE2-Agile-Foundation-valid-vce-dumps.html