No Help, Full Refund
If you failed NABCEP PVIP real exam with our PVIP pass guide, first you can choose to wait the updating of PVIP exam dumps or free change to other dumps if you have other test. If you want to full refund, please within 7 days after exam transcripts come out, and then scanning the transcripts, add it to the emails as attachments and sent to us. After confirmation, we will refund immediately.
One-year free update
If you bought PVIP practice test study materials from our website, you will be allowed to free update your exam dumps one-year. If the latest version of NABCEP PVIP exam dumps released, we will send it your email immediately, you just need to check your email.
24/7 customer assisting
We offer 24/7 customer assisting to support you in case you may encounter some problems, such as downloading or purchasing. If you have any problems please feel free to contact us.
Instant Download NABCEP PVIP Exam Braindumps: Upon successful payment, Our systems will automatically send the product you have purchased to your mailbox by email. (If not received within 12 hours, please contact us. Note: don't forget to check your spam.)
About our products
Our website provides our customers with best PVIP pass collection study materials. Our PVIP exam dumps are written by IT experts who have vast experience and knowledge in the PV Installation Professional (PVIP) Board Certification. The certified experts make sure that the NABCEP PVIP exam cram is updated on a regular basis with PVIP real exam so every customer can prepare PVIP pass guide smoothly. The PVIP practice test will enable you to improve your ability with minimum time spent on PVIP real exam and maximum knowledge gained.
Our website is a professional certification dumps leader that provides NABCEP PVIP exam dumps material and PVIP pass guide for achieving, not an easy way, but a smart way to achieve certification success in PVIP real exam. We are equipped with professionals having vast experience in the PVIP practice test; they are a committed team of individuals that make sure that the customers get the latest PVIP test questions and PVIP test answers. Our website is the single best training online tools to find your PVIP practice test and to study for your PV Installation Professional (PVIP) Board Certification real exam. Our aim is always to provide best quality practice exam products with best customer service.
Difference between test engine and online test engine
Test engine and online test engine both are a simulation of actual test; you can feel the atmosphere of PVIP real exam by test engine and online version. You can only use test engine on the Windows operating system, but online version supports Windows/Mac/Android/iOS operating systems that mean you can practice NABCEP PVIP test questions or test yourself on any electronic equipment. It doesn't limit the number of installed computers or other equipment.
NABCEP PV Installation Professional (PVIP) Board Certification Sample Questions:
1. Most electric service providers require interactive PV equipment to comply with which for interconnection to their distribution grid?
A) UL 16998
B) UL 1741
C) UL 2703
D) UL 60947-1
2. A 15 kW system has a total derate factor of 0.87. After 3 years at 1% degradation/year, what is the output?
A) 12.6 kW
B) 13.2 kW
C) 13.0 kW
D) 12.8 kW
3. A microinverter system uses 30 modules, each rated at 320W, with an inverter efficiency of 96%. The AC output is connected to a 208V three-phase service. What is the total three-phase power output?
A) 8.8 kW
B) 10.0 kW
C) 9.2 kW
D) 9.6 kW
4. A grid-connected PV system on a dwelling is producing 30% less power than expected. The conductors from threes strings of modules enter into a 3-pole fused dc disconnect, and each ungrounded conductor is connected to a separate pole. On the inverter side of the switch terminals, the three strings are combined. The dc disconnect switch is opened. The voltages on the array side of the switch are 440 on string #1, 444V on string #2, and 0V on string #3. The dc disconnect is then closed and the inverter resumes operating, still producing about 30% less power than expected. A clamp-on ammeter is used to measure the dc current of each string of each string of modules where they enter the rooftop junction box. The operating currents of each string are 3.9A for string #1, 3 85A for string #2, and 4.3 A for string #3. What is the MOST likely with the system?
A) String #3 has an open connection and is not contributing any voltage.
B) A ground fault is causing the current from strings #1 and #2 to flow into string #3.
C) Positive and negative output conductors of string #3 are faulted together.
D) There is lower module mismatch in string #3 than in string #1 and #2.
5. A PV system combiner box contains six source circuits, each with an Isc of 8A. The output conductor is 6 AWG THWN-2 copper rated at 90°C. What is the maximum allowable OCPD rating per NEC?
A) 70A
B) 60A
C) 50A
D) 80A
Solutions:
| Question # 1 Answer: D | Question # 2 Answer: D | Question # 3 Answer: C | Question # 4 Answer: C | Question # 5 Answer: B |