Preparation shouldn't drain either resource. Add the SAP Certified Application Associate - Production Planning & Manufacturing with SAP ERP 6.0 EHP7 dumps from PassCollection to your cart and save both time and money — 108 practice questions, focused and efficient in 2026.
SAP C_TSCM42_67 Exam Syllabus Topics:
| Section | Weight | Objectives |
|---|---|---|
| Application Overview and Background | < 8% | - Integration between PP and other modules - Basic PP process flow |
| Material Requirements Planning (PP-MRP) | > 12% | - Firming and planning strategies - MRP run and evaluation - MRP setup and prerequisites |
| Production Orders Basics (PP-SFC) | 8% - 12% | - Production order creation and release - Order confirmation and goods movement |
| Process Orders (PP-PI) | < 8% | - Process order characteristics - Master recipe and resources |
| Material and Capacity Requirements Planning | > 12% | - Demand management - Availability check (ATP) - Capacity planning and evaluation |
| Lean Manufacturing (PP-REM, PP-KAB) | 8% - 12% | - Repetitive manufacturing setup - Kanban process and configuration |
| Production Orders Advanced (PP-SFC) | > 12% | - Order status management - Order settlement and costing - Production order configuration |
| Master Data (LDM) | 8% - 12% | - Material master - Production version - Work center and routing - Bill of Materials (BOM) |
| Basics on SAP Business Processes | < 8% | - SCM and ERP overview |
SAP Certified Application Associate - Production Planning & Manufacturing with SAP ERP 6.0 EHP7 Exam FAQ — What Matters
Registration runs through the vendor's official channels:
The SAP Certified Application Associate - Production Planning & Manufacturing with SAP ERP 6.0 EHP7 is delivered Online proctored via SAP Certification Hub; Onsite at authorized Pearson VUE / SAP testing centers — choose the arrangement that suits you when booking.
Delivery is instant — payment triggers an automatic email within a minute, with unlimited installations and 24/7 assistance if nothing arrives within 2 hours (check spam). Updates arrive the same way: for 365 days, each new version is sent to your mailbox immediately upon release. And if you fail the corresponding C_TSCM42_67 exam within 60 days of purchase, we refund in full: submit a scanned enrollment slip plus the official Score Report PDF within 2 days of the exam, processed within 7 days. Excluded: exams within 3 days of purchase, candidate names that don't match the payer, and free or expired products. You can also exchange for two equal-value products free.
200 USD (CER001 single attempt); 500 USD (CER006 6 attempts) per attempt, 63% to pass. Retakes bill the full fee again — which is why accurate preparation with the 108 practice questions from PassCollection is the economical route.
Yes — a free SAP Certified Application Associate - Production Planning & Manufacturing with SAP ERP 6.0 EHP7 demo is available to download before you decide. Evaluate the questions and answers yourself; every purchase then includes 365 days of free updates, renewable at 50% off afterward.
180 minutes for 80 questions. Practice seriously with the clock running — timed sessions in the PassCollection engine turn time pressure into routine before test day.
Yes:
- TSCM40 - Production Planning & Manufacturing I
- TSCM42 - Production Planning & Manufacturing II
- SCM240 - EHP7 for ERP 6.0: Material Requirements Planning
Official courses consolidate theory; the 108 practice questions for the SAP Certified Application Associate - Production Planning & Manufacturing with SAP ERP 6.0 EHP7 consolidate exam readiness. Use both.
The SAP Certified Application Associate - Production Planning & Manufacturing with SAP ERP 6.0 EHP7 is SAP's certification exam for SAP Certified Application Associate - Production Planning & Manufacturing with SAP ERP 6.0 EHP7, at the Associate level. For IT workers with aspirations, it's essential proof of capability — the line that starts or advances a career. Related credentials include SAP Certified Application Associate - Production Planning & Manufacturing with SAP ERP 6.0 EHP6.
The SAP Certified Application Associate - Production Planning & Manufacturing with SAP ERP 6.0 EHP7 blueprint spans 9 domains — including Material Requirements Planning (PP-MRP) (> 12%), Lean Manufacturing (PP-REM, PP-KAB) (8% - 12%), Material and Capacity Requirements Planning (> 12%). Allocate study time by weighting, and consult the full outline above for every subtopic.
No mandatory prerequisites; recommended basic knowledge of SAP ERP and production processes; typical candidate has up to 3 years of project experience Vendors revise eligibility rules periodically, so confirm the current requirements on the official page (official C_TSCM42_67 exam page) before registering.
SAP Certified Application Associate - Production Planning & Manufacturing with SAP ERP 6.0 EHP7 Sample Questions:
You want to create a new material that - is kept in stock- is externally procured- is used as a component in the bills of material for various final products- must not be sold directly Which standard SAP material type do you use?
- A. ROH (raw material)
- B. FERT (finished product)
- C. NLAG (non-stock material)
- D. HAWA (trading good)
Correct Answer: A 🗳️
In SAP ECC, you calculate the standard available capacity for a work center capacity using the following data:
- Start: 7:00:00 a.m.
- End: 3:00:00 p.m.
- Break duration: 1 hour
- Rate of utilization: 80%
- Overload: 110%
- Number of individual capacities: 1
How large is the standard available capacity?
- A. 8 hours
- B. 5.6 hours
- C. 6.16 hours
- D. 7 hours
Correct Answer: B 🗳️
Which functions can be triggered before releasing a production order? (Choose three)
- A. Stock determination
- B. Selection of a BOM
- C. Confirmation
- D. Scheduling
- E. Selection of a routing
Correct Answer: B,D,E 🗳️
Which property applies for consumption with planning strategy 40 (planning with final assembly)?
- A. Consumption creates a static and binding assignment between the planned independent requirements and the customer requirements for the entire procurement process.
- B. Consumption can increase the total originally planned production quantity.
- C. Consumption takes place with the planning material.
- D. Consumption can reduce the total originally planned production quantity.
Correct Answer: B 🗳️
The availability check during production order creation should use a different scope of check than during order release.
How can you fulfill this requirement?
- A. Maintain appropriate availability checking rules in the production scheduling profile.
- B. Maintain an appropriate availability checking group in the material master.
- C. Maintain appropriate availability checking rules in the order type-dependent parameters.
- D. Maintain appropriate checking rules in checking control for order creation and order release.
Correct Answer: D 🗳️